The
Bayelsa State Executive Council has approved N61billion as variation cost on
the Nembe-Brass road project.
Governor
Diri, who disclosed this on Friday during an inspection of the project, said
the council at its meeting on Wednesday approved a review of the construction
cost, bringing it to N115billion.
Twenty
of the 21km of the first phase of the project has been sand-filled, 6.5km stone
base laid and sand stabilised while work on the second bridge out of the 10 has
commenced.
A
statement by his Chief Press Secretary, Mr. Daniel Alabrah, quoted the governor
as saying he was impressed with the extent of work done by the construction
company, Setraco, unlike when he last visited the project in March this year.
Senator
Diri also said he was satisfied that
funds released for the project were being judiciously utilised and urged the
company to deliver the contract as scheduled.
The
governor equally expressed the optimism that President Bola Tinubu’s promise
that the federal government will partner the state government on the second
phase of the project will be fulfilled.
He
said: “The Commissioner for Works informed me that you wanted to suspend work
because of the variation. The variation you brought was higher than the initial
contract sum.
“I
was very skeptical but he tried to convince me that the variation was not just
that the contractor was looking for money but that it was because of the
changes in our foreign exchange rates.
“So,
we approved the variation in the last state executive council meeting, which
brought the project cost up to N115billion. That means you must justify and
deliver this job as planned.
“You
have achieved so much progress on the 21km stretch, with the first bridge
completed and about to commence the second major bridge, which is 120 metres
long.
“I’m
also happy to hear from you that 6.5km of the road is ready for asphalting and
that sand filling on the road has reached the 20km mark.
“On
the second phase of this road, I had met Mr. President and also communicated to
him. He directed the Minister of Works to do the needful. We are still awaiting
action.
“But
I am convinced that with the interest shown by the president, the second phase
would be awarded by the federal government.”
The
Project Manager of Setraco Nigeria Limited, Mr. Hazen Nadjab, stated that the
company will fulfill its part of the contract and commended the state
government’s effort in ensuring the smooth construction of the road.
Mr.
Nadjab disclosed that the company had requested for extension of the completion
date due to changes in cost of construction but assured that by December this
year, six kilometers of the road would be asphalted.
Also, the Commissioner for Works, ESV Moses Teibowei, stated that with the commitment of the state government and the availability of funds, the project will be completed within the shortest possible time.
Comments:
Leave a Reply