“At the Third Mainland bridge, we have three or four critical elements to be rehabilitated. The first one is the deck, and the deck is about 11 kilometers two. That is dual carriageway, including the ramps, and it has been done by CCECC.
“They have done very beautiful jobs, but we have not concluded. Before the end of March, we’ll be concluding the asphalt milling and the reasphalting.
Umahi added , “But that is not all our commitment there. We are installing the guardrails, we are replacing the lights with solar light, we are going to put some decorative lights too, and then we are going to put CCTV camera both on top and under the bridge to check insecurity and illegal mining of sand, which is causing scouring on the piles and the pipe bits.
“The second job is that some sections of the slab are deflected, and so what we have done is to get an expert to understudy the level of deflection.
“That’s the tendons of the slab that deflected. And so we are going to cut open the slabs, enter and then look at it, scoop it, and then reinstate the tendons of the slab. There’s nothing to worry about. It’s been done at a Eko bridge by Buildwell. So this one is not a threat to us at all.”
The minister also commended what Julius Berger Nigeria Ltd is already doing, which is restoration of deteriorated peirs and peir caps including the cover of peirs and peircaps themselves, and said the piles which he also inspected were the most critical of the works to be done.
Earlier in their respective remarks, the State Controller, Federal Ministry of Works and the representatives of Hitech Construction Nigeria Ltd, Julius Bergger Nigeria Ltd, China Civil Engineering Construction Corporation Ltd, and. Buildwell Nigeria Ltd assured the Honourable Minister that they would continue to work in line with the spirit of excellence, which the Renewed Hope administration of *His Excellency President Asiwaju Bola Ahmed Tinubu is known for.